Proud to be an Exchange MVP
Video Guides
Surveys
Favorite Exchange Blogs
Microsoft Exchange Blogs
Exchange Training
Site Stats
Members : 2Content : 147
Content View Hits : 139944
| The Data Centre – the final road and completion… |
|
|
| Written by Andy Grogan |
| Saturday, 26 December 2009 13:20 |
|
As posted here and here during the mid point of this year I was taken “off radar” from a lot of my Exchange endeavours to work on the design, tendering and technical project management of the re-fit of my companies data centre. I have had a few e-mails from people whom were curious to see how it all panned out, I had indeed planned to do an updated post – but had not found the time until now to write something of any substance. For people whom are joining me here and have not had a look at the previous parts – this is what the server room looked like prior to work beginning in July 2009:
As a summary from where I left off in the in the last part, we had completed the following work items:
All of the above represented quite a lot of work for both the chosen supplier (Comms Room Services) and my team – but, although at this point we were still on course for target completion, we were ahead of schedule (amazingly) – there was still a huge amount of work to do:
To give you a more visual idea of how the project had progressed and indeed what needed to be done the following is the actual “Rocket” diagram which we had been using to provide summary overviews of the project to Chief, Senior and key officers:
At this stage on the above plan, we were at the 11/09/2009 - leaving us with two months with the remaining tasks to hit the final delivery date of 11/11/2009. All of the above represented perhaps the biggest visual changes within the room as the floor was now completed and indeed the "builds" area (which also formed an entry lobby into the data centre) had been constructed. Additionally the ceiling had almost been completed and other key functional aspects of the room had been placed within the room and were waiting commissioning (for example the Fire Suppression systems). During this period we also had to take delivery of our Backup generator – now this might at first seem to be somewhat of an easy task – however we were presented with the following challenges:
All in all it took 4 hours to get the generator onto its plinth (located directly at the back of our Data Centre) – the following are some of the pictures (as you can tell we had some fun): From this point we could all sense that we were in the “home straight” and, cutting a long story short (ish) we met our completion date of the 11/11/2009 – the following are some photos of the final article (barring some minor tidy up): As I mentioned above, this project ranks up there with perhaps the best work that I have been part of. It was one of those rare “IT beasts” where all the stars aligned and things ran like clock work. We had a great supplier, I had a determined and focussed team of people, we ran to budget and time – plus had the support from all our customers and senior officers (managers).
|
| Last Updated on Saturday, 26 December 2009 14:03 |






