The Data Centre – the final road and completion…

As posted here and here during the mid point of this year I was taken “off radar” from a lot of my Exchange endeavours to work on the design, tendering and technical project management of the re-fit of my companies data centre.
Considering the amount of work that was involved (as we had to rebuild the entire facility with all of the existing kit within it – and LIVE) we managed to get from design to tender to project completion within six months – I have to confess that it was and indeed has been one of the most satisfying projects that I have ever worked upon – and indeed took an immense amount of pleasure from the people whom I worked with (both the supplier and my team) along the way.

I have had a few e-mails from people whom were curious to see how it all panned out, I had indeed planned to do an updated post – but had not found the time until now to write something of any substance.

For people whom are joining me here and have not had a look at the previous parts – this is what the server room looked like prior to work beginning in July 2009:

Server-Room-Front-Small

As a summary from where I left off in the in the last part, we had completed the following work items:

  • Removed 9 racks worth of redundant kit from the room
  • Removed all asbestos from the room
  • Removed two trees which were growing out of the roof of the data centre (I am not kidding…)
  • Removed the old ceiling
  • Completed 75% of the new floor
  • Ran the new power cabling from the mains to the room (although at this point it had not been terminated)
  • Installed 45% of the new ceiling
  • Moved all of the kit (servers / Sans / tape libraries / Mid Range AIX servers and Networking devices) into their final positions on the new floor
  • Removed redundant power / networking and fibre from the room (almost 23 miles worth! – yes we measured it!)
  • Installed x 5 condensers units on the roof of the Data Centre
  • Installed all of the pipe work for the new air conditioning
  • Performed x 3 room power downs (one of which included a full site power down) and brought all of our systems back for first thing on Monday
  • Begun the installation of the piping for the fire suppression system
  • Installed most of the re-enforcement for the walls to make them 1 hour fire rated

All of the above represented quite a lot of work for both the chosen supplier (Comms Room Services) and my team – but, although at this point we were still on course for target completion, we were ahead of schedule (amazingly) – there was still a huge amount of work to do:

  • Installation of the new power distribution boards (A & B)
  • Completion of the “plinth” for the new Backup Generator
  • Installation of the new Generator
  • Implementation of the re-enforced floor for the Gas Suppression and the UPS systems
  • Installation of the UPS systems
  • Installation of the Generator Cut over
  • Installation of the Fire Suppression and Fire Control Systems (including Gas Venting and VESDA)
  • Completion of the Floor
  • Completion of the Ceiling
  • Installation of the CCTV and Door access control systems
  • The build of our Prototyping Area (where we would perform server and networking build prior to transportation to the Data Centre)
  • Installation of the new lighting (which includes emergency lighting systems) based upon PIR devices
  • Installation of x 2 new Data Centre doors and one for the builds area (these doors weighed 3 tonnes)
  • Installation of 7 Medusa Patch Racks with 2000 RiT ports and associated CAT5e cabling with 48 ports to each rack in the room
  • Installation of the text and e-mail notification system
  • Test all systems
  • Cut over to the new power feeds
  • Install moisture / flood detection systems
  • Top and tail the room (snagging)

To give you a more visual idea of how the project had progressed and indeed what needed to be done the following is the actual “Rocket” diagram which we had been using to provide summary overviews of the project to Chief, Senior and key officers:

DC&DRrocket

At this stage on the above plan, we were at the 11/09/2009 - leaving us with two months with the remaining tasks to hit the final delivery date of 11/11/2009.
So we ploughed on with out endeavours the following is a "montage" of the progress that we made between 11/09/2009 and 15/10/2009

07092009070
07092009070
07092009071
07092009074
07092009076
IMGP3033
IMGP3035
IMGP3057
IMGP3288
IMGP3297
IMGP3298
IMGP3300
IMGP3302
IMGP3303
IMGP3307
IMGP3309
IMGP3316
IMGP3323
IMGP3520
IMGP3526
IMGP3529
IMGP3530
IMGP3537
W5.25
W5.31
W5.37
W5.39
W5.40
W5.44
W5.45
W6 (11)
W6 (12)
W6 (2)
W6 (22)
W6 (31)
W6 (55)
W6 (6)

All of the above represented perhaps the biggest visual changes within the room as the floor was now completed and indeed the "builds" area (which also formed an entry lobby into the data centre) had been constructed. Additionally the ceiling had almost been completed and other key functional aspects of the room had been placed within the room and were waiting commissioning (for example the Fire Suppression systems).

During this period we also had to take delivery of our Backup generator – now this might at first seem to be somewhat of an easy task – however we were presented with the following challenges:

  • It weighed 6.5 tonnes
  • Turned up on two 18 wheeler articulated lorries (one for the Generator and one for the two fork lift trucks)
  • There is no direct Road Access to our Data Centre – therefore we would have to unload the generator in the main road via the fork lifts and transport it around
  • The road mentioned above is one of the main routes for traffic in our area – the Generator turned up in the peak of rush hour
  • We held the road up of 1 hour
  • The delivery team seemed have had their sense of humour removed, and were perhaps amongst the grumpiest men that I have ever met (perhaps it was because they had to do some work?)

All in all it took 4 hours to get the generator onto its plinth (located directly at the back of our Data Centre) – the following are some of the pictures (as you can tell we had some fun):

IMGP3164
IMGP3164
IMGP3165
IMGP3168
IMGP3169
IMGP3188
IMGP3191
IMGP3212
IMGP3216
IMGP3220
IMGP3227
IMGP3228
W5 (5)
W5.16
W5.17
W5.18
W5.20
W5.24

From this point we could all sense that we were in the “home straight” and, cutting a long story short (ish) we met our completion date of the 11/11/2009 – the following are some photos of the final article (barring some minor tidy up):

IMGP3534
IMGP3534
IMGP3535
IMGP3536
IMGP3544
IMGP3547
IMGP3550
IMGP3551
IMGP3555
IMGP3556
IMGP3559
IMGP3564
IMGP3565
IMGP3567

As I mentioned above, this project ranks up there with perhaps the best work that I have been part of. It was one of those rare “IT beasts” where all the stars aligned and things ran like clock work. We had a great supplier, I had a determined and focussed team of people, we ran to budget and time – plus had the support from all our customers and senior officers (managers).



Add this page to your favorite Social Bookmarking websites

Last Updated (Saturday, 26 December 2009 14:03)

 
English (United Kingdom)